When Changing Finish Date, the Date Is Set Ahead One Calendar Day When Using a 24/7 Calendar (Doc ID 2497222.1)

Last updated on JUNE 30, 2021

Applies to:

Primavera P6 Enterprise Project Portfolio Management - Version 8.2.0.0 and later
Primavera P6 Enterprise Project Portfolio Management Cloud Service - Version 16.2.0.0 and later
Information in this document applies to any platform.

Symptoms

ACTUAL BEHAVIOR

For a project with a 24x7 calendar and Time is not being displayed in the application, when setting a Finish Date on a not-started activity, the date is being set to the next calendar day.

EXPECTED BEHAVIOR:

When setting a Finish Date, the date should be set to the selected day.

 

The issue can be reproduced at will with the following steps:

  1. Open a project, display the Activities view, and highlight an activity.
  2. Make sure the Finish Date column is visible.
  3. Set the Finish Date for the activity to October 8.
  4. After clicking Select on the date, the Finish Date is set to one day ahead, October 9.
  5. Display the Time via User Preferences (Edit > User Preferences > Dates > Time).
  6. The Finish Date for the activity is set to October 9 00:00.
  7. Set the Finish Date to October 8.
  8. After clicking Select on the date, the Finish Date is correctly set to October 8 23:59.

Cause

To view full details, sign in with your My Oracle Support account.

Don't have a My Oracle Support account? Click to get started!


My Oracle Support provides customers with access to over a million knowledge articles and a vibrant support community of peers and Oracle experts.