Excel Export Start/Finish Dates Don't Show 'A' to Indicate Actual Dates. (Doc ID 2508738.1)

Last updated on APRIL 06, 2020

Applies to:

Primavera P6 Professional Project Management - Version 15.1.0.0 and later
Primavera P6 Enterprise Project Portfolio Management - Version 15.1.0.0 and later
Primavera P6 Enterprise Project Portfolio Management Cloud Service - Version 15.1.0.0 and later
Information in this document applies to any platform.

Symptoms

When Exporting date fields to Excel format, the "Start" and "Finish" fields are not displaying the 'A' value to indicate Actual Start and Actual Finish.

Steps:

  1. Sign in to P6 Pro Client.
  2. Open a Project and ensure some Activities have an Actual Start.
  3. Export the Activities to Excel format.
  4. Open the Excel file.
  5. Note that the Activities with an "Actual Start" are not showing an 'A' in the Start date field.

Changes

 

Cause

To view full details, sign in with your My Oracle Support account.

Don't have a My Oracle Support account? Click to get started!


In this Document
Symptoms
Changes
Cause
Solution