The PMDA E2B (R3) nullification report which was scheduled manually from the regulatory report tab has already been submitted to agency.

This case received the follow-up information.

Although the current case data is matched with the criteria of the reporting rule, a new initial E2B (R3) dose not automatically schedule.


Note:
------------
This issue does not occur if the nullification report had been scheduled automatically (such as when deleting the case and/or by AG service).



Steps:
------------
1. Create a case
2. Enter the mandatory information for PMDA E2B (R3)
3. Save the case
4. Go to the regulatory report tab
5. Press the [Auto Schedule] button
6. The initial report was scheduled by reporting rule
7. Close the case
8. Submit and transmit the report
9. Receive ACK

10. Open the case
11. Go to the regulatory report tab
12. Schedule the nullification report manually
13. Save the case
14. Generate the final report
15. Close the case
16. Submit and transmit the report
17. Receive ACK

18. Open the case
19. Go to the regulatory report tab
20. Press the [Auto Schedule] button

No initial report was scheduled even though the current case data is matched with the criteria of the reporting rules.

Changes

 

Cause

To view full details, sign in with your My Oracle Support account.

Don't have a My Oracle Support account? Click to get started!


In this Document
Symptoms
Changes
Cause
Solution
References


My Oracle Support provides customers with access to over a million knowledge articles and a vibrant support community of peers and Oracle experts.