Symptoms

When retrieving the PlannedValueCost using the P6 Web Services ActivityService, the value randomly changes. While troubleshooting the issue it appears there are some other fields which are calculated based off baseline data that also change randomly. See example below of the fields that change randomly.

NOTE: This issue also seems to cause a performance issue in some cases.

For example:

GOOD PLANNEDVALUECOST:

           <AccountingVariance>4350.528507033479</AccountingVariance>          
           <AccountingVarianceLaborUnits>48.500840749995405</AccountingVarianceLaborUnits>
           <PlannedValueCost>551773.4829790335</PlannedValueCost>
           <PlannedValueLaborUnits>5555.500840749995</PlannedValueLaborUnits>          
           <SchedulePerformanceIndex>1.009947038324049</SchedulePerformanceIndex>          
           <SchedulePerformanceIndexLaborUnits>1.0053307387684614</SchedulePerformanceIndexLaborUnits>
           <ScheduleVariance>5488.5119813864585</ScheduleVariance>          
           <ScheduleVarianceIndex>0.009947038324049026</ScheduleVarianceIndex>          
           <ScheduleVarianceIndexLaborUnits>0.005330738768461294</ScheduleVarianceIndexLaborUnits>          
          <ScheduleVarianceLaborUnits>29.614923710005314</ScheduleVarianceLaborUnits>


WRONG PLANNEDVALUECOST:

           <AccountingVariance>602.9148460341385</AccountingVariance>          
           <AccountingVarianceLaborUnits>-14.452599064388778</AccountingVarianceLaborUnits>
           <PlannedValueCost>548025.8693180342</PlannedValueCost>
           <PlannedValueLaborUnits>5492.547400935611</PlannedValueLaborUnits>          
           <SchedulePerformanceIndex>1.016853448275862</SchedulePerformanceIndex>          
            <SchedulePerformanceIndexLaborUnits>1.0168534482758622</SchedulePerformanceIndexLaborUnits>
           <ScheduleVariance>9236.1256423858</ScheduleVariance>          
           <ScheduleVarianceIndex>0.016853448275862007</ScheduleVarianceIndex>          
           <ScheduleVarianceIndexLaborUnits>0.016853448275862166</ScheduleVarianceIndexLaborUnits>          
           <ScheduleVarianceLaborUnits>92.5683635243895</ScheduleVarianceLaborUnits>


STEPS
-----------------------
The issue can be reproduced at will with the following steps:
1. Setup a SoapUI ActivityService Request
2. Run the request continuously and the PlannedValueCost will randomly change from the correct value to an incorrect value and then back.

Changes

 

Cause

To view full details, sign in with your My Oracle Support account.

Don't have a My Oracle Support account? Click to get started!


In this Document
Symptoms
Changes
Cause
Solution
References


My Oracle Support provides customers with access to over a million knowledge articles and a vibrant support community of peers and Oracle experts.