Symptoms

12.1.3.9.2 or higher

PROBLEM
-------------
Supply is not created to meet EDD plan requirements

STEPS
------------
Plan type: Constrained(Without Detailed Scheduling)
Overwrite - None
850 days /0w/0p
DTF and PTF
Plan run date 30-APR-2019

Plan option - Enforce purchasing lead time constraints is checked
MSC: Use FIFO Pegging: No
MSO: Lead Time Control: Do not violate minimum processing times
MRP:Firm Planned Order Time Fence: Yes
MSO: Net All Firm Supplies Before Creating Planned Order: All Supply Types


RESULTS
1. ASCP Should not create any planned orders before the dates of the Firmed Planned Order created in the  plan - they are on 01-JUL-2019
2. ASCP is not creating any Planned Order for Demands for forecast between 01-Jul-2019 until APR-2020 - builds a negative balance of 13,000+ Then one planned order in 14-APR-2020 balances all the negative balance.  - Item has very long lead times - over 250 calendar days
This is not what we are expecting. We want ASCP to create planned orders after 01-Jul-2019 considering the supply demand available. We want ASCP to cover for Demands as and when the due dates are. Refer Attached export of ASCP PWB.


Cause

To view full details, sign in with your My Oracle Support account.

Don't have a My Oracle Support account? Click to get started!


In this Document
Symptoms
Cause
Solution


My Oracle Support provides customers with access to over a million knowledge articles and a vibrant support community of peers and Oracle experts.