Copy Project Completes Successfully But The Activities And Assignments Are Not Copied (Doc ID 2538004.1)

Last updated on JULY 29, 2019

Applies to:

Primavera P6 Enterprise Project Portfolio Management - Version 18.8 to 18.8.7.0 [Release 18.8]
Information in this document applies to any platform.

Symptoms

After copying a project or adding baselines, the job service completes successfully, but activities and assignments are not copied/created and the following error occurs in the job's log file:

Copy Activities FAILED
Copy Assignments FAILED

Below error messages can be found from the P6WebAccess.html log.

ERROR com.primavera.infr.dbcrud.copy.binding.custom.CustomStep ?:? Unexpected error executing Custom Step
org.springframework.dao.EmptyResultDataAccessException: Incorrect result size: expected 1, actual 0
at org.springframework.dao.support.DataAccessUtils.nullableSingleResult(DataAccessUtils.java:97)
at org.springframework.jdbc.core.JdbcTemplate.queryForObject(JdbcTemplate.java:468)
at org.springframework.jdbc.core.JdbcTemplate.queryForObject(JdbcTemplate.java:474)
at com.primavera.infr.dbcrud.core.JDBCTemplateWithSQLTracking.queryForObject(JdbcTemplateDAO.java:775)
at com.primavera.infr.dbcrud.core.JdbcTemplateDAO.getAuditOptions(JdbcTemplateDAO.java:225)
at com.primavera.infr.dbcrud.copy.binding.custom.CustomStep.call(CustomStep.java:493)
at com.primavera.infr.dbcrud.copy.binding.custom.CustomStep.call(CustomStep.java:35)
at com.primavera.infr.threadpool.SEAdapter$CallableAdapter.execute(SEAdapter.java:134)
at com.primavera.infr.threadpool.ThreadPoolImpl.run(ThreadPoolImpl.java:343)
at java.lang.Thread.run(Thread.java:748)

 

The issue can be reproduced at will with any one of following steps:

A.
1). Login to P6 (Professional or Web).
2). Select a project then copy it.
3). The CopyProject job completes successfully.
4). Observe the reported issue.

B.
1) Create a new project
2) Add five activities
3) Go to Maintain baseline
4) Add baseline
5) Convert project to baseline
6) Open SQL Studio, open task table for the baseline project. This contains no tasks

C.
1) Create a new project
2) Add five activities
3) Copy the new created project
4) Open the copied project
5) No activities showed

 

Cause

To view full details, sign in with your My Oracle Support account.

Don't have a My Oracle Support account? Click to get started!


In this Document
Symptoms
Cause
Solution
References


My Oracle Support provides customers with access to over a million knowledge articles and a vibrant support community of peers and Oracle experts.