Symptoms

When updating the fields in Risk Module of P6 EPPM to BI Publisher, the Dates are not populated. The problem appears to be with the Data Model in BI Publisher labeled as "Qualitative Risk Report". Since this was a canned Data Model shipped with the program, it cannot be corrected

The issue is with all the dates field: Start Date, Finish Date, Planned Start Date, Planned Finish date.

Normally, the report should have the Dates populated just like other fields are.

STEPS TO REPRODUCE
--------------------------
The issue can be reproduced at will with the following steps:
1. Entered the data in the Risk Response Actions fields for Start and Finish Date
2. Published Projects/Summarize Projects
3. Open BI Publisher and Navigate to Catalog; P6Reports; Project and Select Data Model "Qualitative Risk Report" and click on Edit
4. In the editor, select the data tab; select the project from the drop box;
5. Select "View"

Additional details
--------------------

BI Publisher version is 12.2.1.4.0 It is not possible to see the correct results in the following two cases:
1. While running the report from P6 and expect the results in BI Published
2. While running the same report in BI Publisher

Cause

To view full details, sign in with your My Oracle Support account.

Don't have a My Oracle Support account? Click to get started!


In this Document
Symptoms
Cause
Solution
References


My Oracle Support provides customers with access to over a million knowledge articles and a vibrant support community of peers and Oracle experts.