On : 12.2.6 version, Materials Requirements Plan in PROD

Users created an item and BOM for a particular make item. They created a sales order for the end item. They created a wip discrete job for the end item. They loaded the sales order to an MDS and attached the MDS to an MRP plan and ran it. The MRP planners workbench did plan for the sales order, wip job and some (about 6) of the direct components for the BOM but it did not plan for about 20 direct components. They have the items all set to be MRP planned and the BOM is setup with all 26 direct items

Example bom
==========
JMake
-Comp1
-Comp2
-Comp3
-Comp4

After creating sales order for qty = 1 JMake due 28-JUN-2019, users also created wip job qty = 1 for JMake sure 28-JUN-2019.  The sales order was successfully loaded to an MDS and the MDS attached and run on an MRP Plan.  However the plan only planned for JMake, Comp1 and Comp2.  No supply demand was found for Comp3 nor Comp4

EXPECTED BEHAVIOR
-----------------------
Expected all components to have demand/supply planned in the MRP workbench

STEPS
-----------------------
The issue can be reproduced at will with the following steps:
1. Create item/bom
2. Create sales order and end item wip job
3. Load MDS and attach and run to an MRP Plan
4. Some components are planned in the workbench but many are not


Changes

 

Cause

To view full details, sign in with your My Oracle Support account.

Don't have a My Oracle Support account? Click to get started!


In this Document
Symptoms
Changes
Cause
Solution