P6 Unifier Integration Via Gateway: Partial WBS Hierarchy Creates In Wrong Order On Unifier Side (Doc ID 2561786.1)

Last updated on NOVEMBER 05, 2019

Applies to:

Primavera Unifier - Version 18.8 and later
Information in this document applies to any platform.

Symptoms

ACTUAL BEHAVIOR
---------------
When pushing P6 WBS into the Unifier Cost Sheet via Gateway, with the Project Preferences - Integrations - Summary sheet Integration - Synchronise WBS Hierarcy set to "Partial" , the WBS on the Unifier side gets created in some strange order, and not the order set in P6.

It works fine when pushing the "Complete" WBS Hierarchy, but not when pushing "Partial" WBS Hierarchy.

EXPECTED BEHAVIOR
-----------------------
WBS hierarchy in Cost Sheet should be in the same order as in P6.

STEPS
-----------------------
The issue can be reproduced at will with the following steps:

  1. Prepare the schedule in P6.
  2. Go to the WBS view and set the checkboxes on the WBS levels needed to be pushed to Unifier.
  3. Set Project Preferences, Integrations, Summary Sheet Integration - Synchronise WBS Hierarcy set to "Partial".
  4. Use Exchange Data to push the WBS to Unifier.

Changes

 

Cause

To view full details, sign in with your My Oracle Support account.

Don't have a My Oracle Support account? Click to get started!


In this Document
Symptoms
Changes
Cause
Solution
References


My Oracle Support provides customers with access to over a million knowledge articles and a vibrant support community of peers and Oracle experts.