Goal
ACTUAL BEHAVIOR
When attempting to update Schedule Duration attribute with large number on Activities using Gantt, Chart, some user are not able to update
and below error occurs.
ERROR
Your Update cannot be completed. You do not have the appropriate modify privileges on one or more project activities or attributes.Return to Gantt and validate your authority to modify certain projects
FACT
1. Activity that is getting error has a root project
2. Adding Activities.General Info.Schedule Status Reason to Modify privilege for Activities Object can workaround the error
STEPS
The issue can be reproduced at will with the following steps:
1. Login to Web Client
2. Open an activity on Gantt Chart
3. Update Schedule Duration attribute to large number ans save
Solution