ToDO TD-PYUPL Is Completed Even If Its 'Being Worked On'
(Doc ID 2584721.1)
Last updated on SEPTEMBER 22, 2022
Applies to:
Oracle Utilities Customer Care and Billing - Version 2.5.0.2.0 to 2.6.0.1.0 [Release 2.5 to 2.6]Information in this document applies to any platform.
Symptoms
On : CCB 2.5.0.2.0 version, TD - To Do
TD-PYUPL Batch: ToDO's are completed even if they are in 'Being worked on' status.
ACTUAL BEHAVIOR
---------------
The batch - TD-PYUPL is scheduled to run 3 times a day - 08:00 AM, 02:00 PM, 04:00 PM. Issue is that, To Dos created by this batch are getting Completed by its next run irrespective of the of To Do status - Open or 'Being worked On'. So, if user has started working on To Do & assigned to other user/Role by adding Information into it, will also be completed without any checks.
EXPECTED BEHAVIOR
-----------------------
ToDo's which are in "Being worked On" status are not closed on subsequent batch run.
STEPS
-----------------------
The issue can be reproduced at will with the following steps:
1. 17 to Do of To Do Type TD-PYUPL Present in the system and out of it 5 are in open but rest all in Completed Status
2. Rest all completed To Do Type
3. Running the BATCH: TD-PYUPL
4. Checking the To Do List. The 5 Open To Do are Completed and 5 more To Do added to the existing count of 17 so we have now 22 To Do of To Do Type TD-PYUPL with 5 Open and rest all completed.
Cause
To view full details, sign in with your My Oracle Support account. |
|
Don't have a My Oracle Support account? Click to get started! |
In this Document
Symptoms |
Cause |
Solution |
References |