Minimum Level Set In Inventory Level Form For Days Of Supply Is Not Respected
(Doc ID 2585744.1)
Last updated on SEPTEMBER 12, 2019
Applies to:
Oracle Inventory Optimization - Version 12.2 and laterInformation in this document applies to any platform.
Symptoms
PROBLEM
-------------
Minimum Level Days of Supply Set in Inventory Level form under Inventory Optimization is Not Respected by IO Plan..
In Setup / Inventory Levels - set Minimum Days of supply (DoS) for Item set is 30 and Maximum - 40
IO Horizontal Plan shows Target Safety Stock (days of supply) is much less than 30.
STEPS
--------
1. Setup inventory levels
2. Run plan
3. check results in HZ plan and see 30 days is not honored
EXPECTED BEHAVIOR
----------------------------
SS level should have 30 days for field Projected and Target Days Of Supply
Cause