PS 12.2.6 C661/C654

The precedence relationship Ends At End is not respected in the below scenario:

Steps
------
1) Firm Start Date on operation 20 is 4/27/18
2) Firm Start Date on operation 30 is 5/24/18
3) All operations are open (no Active operations)
4) Precedence relationship between operation 20 and 30 is Ends At End
5) Solve Model
6) Verify, the precedence relationship Ends At End between operation 20 and
30 is not respected.The firms start dates on operations 20 and 30 are
respected. Also, the WO on operation number 20 is 'Green' whereas WO on
operation number 30 is 'Red'.


Desired Outcome
---------------------------
The precedence relationship Ends At End should be respected in the above scenario

Cause

To view full details, sign in with your My Oracle Support account.

Don't have a My Oracle Support account? Click to get started!


In this Document
Symptoms
Cause
Solution
References


My Oracle Support provides customers with access to over a million knowledge articles and a vibrant support community of peers and Oracle experts.