My Oracle Support Banner

Unassigned Resources Appear in Leveling Log in Copied Project (Doc ID 2605922.1)

Last updated on NOVEMBER 04, 2019

Applies to:

Primavera P6 Enterprise Project Portfolio Management - Version 18.8 to 18.8.13.0 [Release 18.8]
Primavera P6 Enterprise Project Portfolio Management Cloud Service - Version 18.8 to 18.8.13.0 [Release 18.8]
Primavera P6 Professional Project Management - Version 18.8 to 18.8.13.0 [Release 18.8]
Information in this document applies to any platform.

Symptoms

ACTUAL BEHAVIOR

When leveling a copied project, the original resources that were leveled in the original project appear in the leveling log as also being leveled.

EXPECTED BEHAVIOR

Expect only selected resources to be included in the leveling log.

STEPS

The issue can be reproduced at will with the following steps:

  1. Log into P6 Pro.
  2. Level a project.
  3. Copy project.
  4. Level in new project, choosing not to level resources that were leveled in original project.
  5. Resources form original project appear as leveled.

Changes

 

Cause

To view full details, sign in with your My Oracle Support account.

Don't have a My Oracle Support account? Click to get started!


In this Document
Symptoms
Changes
Cause
Solution
References


My Oracle Support provides customers with access to over a million knowledge articles and a vibrant support community of peers and Oracle experts.