Which Calendar Is Used To Convert Durations To Hours When The 'Durations Format' Is Not Set To Hours? (Doc ID 2631986.1)

Last updated on APRIL 06, 2020

Applies to:

Primavera P6 Professional Project Management - Version 18.8 and later
Primavera P6 Enterprise Project Portfolio Management Cloud Service - Version 18.8 and later
Primavera P6 Enterprise Project Portfolio Management - Version 18.8 and later
Information in this document applies to any platform.

Goal

Which calendar is used to convert lag duration to hours when the user preferences duration format is using any 'Unit of Time' other than "Hour"?

Solution