Exporting To Microsoft Project XML Exports The Planned Finish Date For The Finish Date Field (Doc ID 2645359.1)

Last updated on APRIL 06, 2020

Applies to:

Primavera P6 Professional Project Management - Version 18.8.11.0 and later
Information in this document applies to any platform.

Symptoms

Exporting a project to MSP XML format uses the Planned Finish date for the Finish date field.

STEPS

  1. Sign in to P6 Pro Client connected to a PPM DB.
  2. Create or open a project that has an activity with different Finish date than Planned Finish.
  3. Export the project to MSP XML 2002/3 format.
  4. Check the Finish date fields (showing Planned Finish instead of Finish).

Cause

To view full details, sign in with your My Oracle Support account.

Don't have a My Oracle Support account? Click to get started!