Dates Is Not Calculating Correctly In Supplier Scheduling - All Dates For Future Supply Show Same Date Starting 30-APR-2020 (Doc ID 2652925.1)

Last updated on APRIL 01, 2020

Applies to:

Oracle Advanced Supply Chain Planning - Version 12.1.3 and later
Information in this document applies to any platform.

Symptoms

Using Purchasing and Advanced Supply Chain Planning

Forecast is not Calculating Correctly in Supplier Scheduling

KEY DATA FROM MRP_RECOMMENDATIONS

INVENTORY_ITEM_ID 1234
ORGANIZATION_ID 100
COMPILE_DESIGNATOR - PLAN A

NEW_DOCK_DATE NEW_SCHEDULE_DATE
2-Apr-20      7-Apr-20
9-Apr-20    14-Apr-20
16-Apr-20  21-Apr-20
23-Apr-20  28-Apr-20
30-Apr-20   5-May-20
30-Apr-20  12-May-20
30-Apr-20  19-May-20
30-Apr-20  26-May-20
30-Apr-20   2-Jun-20
30-Apr-20   9-Jun-20
30-Apr-20  15-Jun-20
30-Apr-20  22-Jun-20
30-Apr-20   6-Jul-20
30-Apr-20  13-Jul-20
30-Apr-20  20-Jul-20

See how Dock_Date gets 'stalled' at 30-APR - even though Due Date (new_schedule_date) keeps moving forward.
-- Dock Date (or Firm_date if populated) is what is used in supplier scheduling

They confirm that no Global ASL is being used and no capacity /calendar setup in an ASL that could effect the dock date.

Cause

To view full details, sign in with your My Oracle Support account.

Don't have a My Oracle Support account? Click to get started!


In this Document
Symptoms
Cause
Solution
References


My Oracle Support provides customers with access to over a million knowledge articles and a vibrant support community of peers and Oracle experts.