The P6PRMAUDIT_FULL Table Is Not Populating Correctly in the P6 Database
(Doc ID 2671911.1)
Last updated on MARCH 22, 2022
Applies to:
Primavera P6 Enterprise Project Portfolio Management - Version 18.8 to 18.8.18.2 [Release 18.8]Information in this document applies to any platform.
Symptoms
ACTUAL BEHAVIOR
In the P6PRMAUDIT_FULL table, the OLD_VALUE and NEW_VALUE data do not populate on the correct row. The OLD_VALUE for 'cstr_date' is correct, but the NEW_VALUE displayed is actually the new value for the preceding row ('act_work_qty'). The NEW_VALUE in the row for 'remain_work_qty' is the actual finish date updated in the P6 Application.
EXPECTED BEHAVIOR
The table should be populated with the proper values.
Changes
Cause
To view full details, sign in with your My Oracle Support account. |
|