Primary Baseline Bar is Not Positioned Correctly After Updating Project
(Doc ID 2679942.1)
Last updated on JUNE 18, 2020
Applies to:
Primavera P6 Enterprise Project Portfolio Management - Version 18.8.9.0 and laterPrimavera P6 Enterprise Project Portfolio Management Cloud Service - Version 18.8.9.0 and later
Information in this document applies to any platform.
Symptoms
ACTUAL BEHAVIOR
---------------
Primary baseline bar is not positioned correctly (behave as instead) when scheduling with later DD after updating project with XER file.
EXPECTED BEHAVIOR
-----------------------
Primary baseline bar should position correctly.
STEPS
-----------------------
The issue can be reproduced at will with the following steps:
- Login to P6 Pro for EPPM.
- Create a project, add 3 activities, link them together, schedule it.
- Create new baseline from the current project and assign it as both project baseline and primary baseline.
- Export the project to XER file.
- Import the XER file exported in step 4 with the option "update existing project".
- Schedule project with a later DD and check the primary baseline bar in GANTT chart view.
- Notice that the primary baseline bar does not position correctly.
Cause
To view full details, sign in with your My Oracle Support account. |
|
Don't have a My Oracle Support account? Click to get started! |