Moving Gate to Weekend In Gantt Chart Makes Schedule Start Date Later Then Schedule End Date Affecting Its Related Projects Not Able to Open in Gantt Chart (Doc ID 2684393.1)

Last updated on JUNE 24, 2020

Applies to:

Oracle Agile Product Portfolio Management - Version 9.3.6.0 and later
Information in this document applies to any platform.

Symptoms

Actual Behavior
On Gantt Chart, when moving a gate activity under weekend date and save, impacts that activity to save schedule start date later than schedule end date.

This will cause the parent activity / root activity using that gate activity not able to open the whole activity in Gantt Chart.


Steps
The issue can be reproduced at will with the following steps:
1. Login to admin user in Web Client
2. Open program : Program01 which have below activity on Schedule tab.

Schedule Name          Start                End
-----------------------------------------------------------------------
Task01                       01/16/2020     01/23/2020
Gate01                       01/23/2020
Task02                       01/24/2020     01/30/2020

3. Open Gantt Chart in Full Lock mode for program : Program01

4. Add a new gate : Gate01 and drag and move this activity under Task01 in weekend date : 01/17/2020 and save. Close Gantt Chart.

5. Run SQL

NAME           SCH_START_DATE           SCH_END_DATE
-------------------------------------------------------------------
Gate01        20-01-18                        20-01-17

==> schedule start date is being saved later than schedule end date.

6. Try to open program : Program01 again in Gantt Chart in Full Lock Mode. Gantt Chart will not open.



Cause

To view full details, sign in with your My Oracle Support account.

Don't have a My Oracle Support account? Click to get started!


In this Document
Symptoms
Cause
Solution
References


My Oracle Support provides customers with access to over a million knowledge articles and a vibrant support community of peers and Oracle experts.