Schedule Comparison Lists Changes For Calendars When None Were Made (Doc ID 2685808.1)

Last updated on AUGUST 03, 2020

Applies to:

Primavera P6 Professional Project Management - Version 17.7 and later
Primavera P6 Enterprise Project Portfolio Management - Version 17.7 and later
Primavera P6 Enterprise Project Portfolio Management Cloud Service - Version 17.7 and later
Information in this document applies to any platform.

Symptoms

ACTUAL BEHAVIOR

When running Schedule Comparison, the report lists Calendar Names have changed when the Old and New values are still the same.

EXPECTED BEHAVIOR

Do not expect calendar to show up in report as no changes have been made.

STEPS

The issue can be reproduced at will with the following steps:

  1. Log into Visualizer.
  2. Run Schedule Comparison Report.
  3. See differences listed for calendars, even though no changes have been made.

Cause

To view full details, sign in with your My Oracle Support account.

Don't have a My Oracle Support account? Click to get started!