Internal Sales Order Schedule Ship Date Is Moved By Plan And Not Using Ship Method Intransit Time To Determine Suggested Due Date / Schedule Ship Date (Doc ID 2700725.1)

Last updated on SEPTEMBER 04, 2024

Applies to:

Oracle Advanced Supply Chain Planning - Version 12.1.3 and later
Information in this document applies to any platform.

Symptoms

Any release

PROBLEM
-------------
ASCP is not scheduling ISO / IR pair correctly
We have ISO with same due date of IR - ignoring the 40 day intransit time.
We have supply of component in ISO org to make and ship it in time to honor 40 days


STEPS
--------
ECC plan
PTF, DTF checked
Overwrite - None
demand priority pegging
120 days / 8 wks / 4 periods

Example:
The IR  due date is 24-AUG
Sales order - ISO should not have moved out from 15-JUL -- it has 40 days intransit time
 the item  supply pegs to component 7582 which has supply scheduled on 23-JUN - plenty of time to make 8971 and ship on time on 15-JUL
ISO  24-AUG
  |_ Planned Order  24-AUG
  |_Planned Order Demand  24-AUG
  |_Internal Req 23-JUN

Cause

To view full details, sign in with your My Oracle Support account.

Don't have a My Oracle Support account? Click to get started!


In this Document
Symptoms
Cause
Solution
References


My Oracle Support provides customers with access to over a million knowledge articles and a vibrant support community of peers and Oracle experts.