Jobs Submitted via P6 Professional for EPPM Are Stuck in a "Pending" Status.
(Doc ID 2705484.1)
Last updated on MAY 17, 2023
Applies to:
Primavera P6 Enterprise Project Portfolio Management - Version 18.8.14.0 and laterInformation in this document applies to any platform.
Symptoms
ACTUAL BEHAVIOR
When attempting to copy a baseline via P6 Professional, the job is stuck in a "Pending" status under Tools --> Job Status.
EXPECTED BEHAVIOR
The baseline copy should complete as expected.
STEPS
The issue can be reproduced at will with the following steps:
1. Login to P6 Professional for EPPM.
2. Open a project.
3. Click Project --> Maintain Baselines.
4. Highlight a baseline and click "Copy".
5. Observe the process never completes and it shows as "Pending" under Tools>Job Status
Cause