In P6 Professional's Resource Assignments View When Timescale Is Montlhy Some Bucket Intervals Do Not Allow Editing (Doc ID 2715425.1)

Last updated on OCTOBER 28, 2020

Applies to:

Primavera P6 Professional Project Management - Version 19.12 to 19.12.7.0 [Release 19.12]
Primavera P6 Enterprise Project Portfolio Management - Version 19.12 to 19.12.7.0 [Release 19.12]
Primavera P6 Enterprise Project Portfolio Management Cloud Service - Version 19.12 to 19.12.7.0 [Release 19.12]
Information in this document applies to any platform.

Symptoms

When trying to edit Monthly bucket intervals with hours in the Resource Assignments view and when the Timescale is set to Months (e.g., Year/Month) some of the bucket intervals do not allow editing.

STEPS
-----------------------
The issue can be reproduced at will with the following steps:

  1. Login to P6 Professional
  2. Open a Project and navigate to Resource Assignments view.
  3. Set Timescale to Monthly and edit planned value bucket intervals
  4. Result is unable to edit some of the Monthly bucket intervals



Cause

To view full details, sign in with your My Oracle Support account.

Don't have a My Oracle Support account? Click to get started!


In this Document
Symptoms
Cause
Solution