When Using Apply Actuals, the Application Recalculates Wrong at Completion Units and Remaining Units
(Doc ID 2735447.1)
Last updated on JANUARY 26, 2021
Applies to:
Primavera P6 Enterprise Project Portfolio Management - Version 19.12.3.0 to 19.12.7.0 [Release 19.12]Primavera P6 Enterprise Project Portfolio Management Cloud Service - Version 19.12.3.0 to 19.12.7.0 [Release 19.12]
Information in this document applies to any platform.
Symptoms
ACTUAL BEHAVIOR:
When using Apply Actuals, the application recalculates wrong At Completion Units and Remaining Units.
This makes it impossible to track Units in Projects.
STEPS TO REPRODUCE:
- Create a Project with one Activity.
- Assign a Resources X and Y on this Activity.
- Resource X have Budgeted Units = 100h.
- Resource Y have Budgeted Units = 0h.
- Update the Resource Y on the Timesheet with 5h.
- Apply Actuals + 1 week.
- Actual Units for Resource X is 0, but At completion Units and Remaining Units is 95. This is wrong.
- Actual Units for Resource Y is 5.
Cause
To view full details, sign in with your My Oracle Support account. |
|
Don't have a My Oracle Support account? Click to get started! |