When Using Apply Actuals, the Application Recalculates Wrong at Completion Units and Remaining Units (Doc ID 2735447.1)

Last updated on JANUARY 26, 2021

Applies to:

Primavera P6 Enterprise Project Portfolio Management - Version 19.12.3.0 to 19.12.7.0 [Release 19.12]
Primavera P6 Enterprise Project Portfolio Management Cloud Service - Version 19.12.3.0 to 19.12.7.0 [Release 19.12]
Information in this document applies to any platform.

Symptoms

ACTUAL BEHAVIOR:

When using Apply Actuals, the application recalculates wrong At Completion Units and Remaining Units.
This makes it impossible to track Units in Projects.

STEPS TO REPRODUCE:

  1. Create a Project with one Activity.
  2. Assign a Resources X and Y on this Activity.
  3. Resource X have Budgeted Units = 100h.
  4. Resource Y have Budgeted Units = 0h.
  5. Update the Resource Y on the Timesheet with 5h.
  6. Apply Actuals + 1 week.
  7. Actual Units for Resource X is 0, but At completion Units and Remaining Units is 95. This is wrong.
  8. Actual Units for Resource Y is 5.

Cause

To view full details, sign in with your My Oracle Support account.

Don't have a My Oracle Support account? Click to get started!