Planning ODS Load process running longer
(Doc ID 2745891.1)
Last updated on MAY 17, 2023
Applies to:
Oracle Advanced Supply Chain Planning - Version 12.2.6 and laterInformation in this document applies to any platform.
Symptoms
ACTUAL BEHAVIOR
Collections in taking extraordinarily long. There has been a somewhat gradual increase over the last 15 months, and it degraded further with the addition of a new organization into the Oracle instance.
There are two specific programs which are taking much longer than they used to.
Planning ODS Load takes 90 minutes, though the load workers finish in less than 30 minutes.
EXPECTED BEHAVIOR
Expect that the Planning ODS completes in short time.
STEPS
1. Run Standard Data Collection process
Changes
Cause
To view full details, sign in with your My Oracle Support account. |
|
Don't have a My Oracle Support account? Click to get started! |
In this Document
Symptoms |
Changes |
Cause |
Solution |
References |