Symptoms

ACTUAL BEHAVIOR

Setting a custom date for Timescale start/finish in Page Setup directs the user to the year 1899.

EXPECTED BEHAVIOR

The current year should be displayed.

 

The issue can be reproduced at will with the following steps:

  1. Login to P6 Pro.
  2. Open a project and navigate to the Activities view.
  3. Click Page Setup > Options.
  4. Click the ellipses icon [...] for Timescale start/finish, choose CD or any other existing tagged date.
  5. Click [...] again and choose Custom date.
  6. Observe the reported behavior.

Cause

To view full details, sign in with your My Oracle Support account.

Don't have a My Oracle Support account? Click to get started!


My Oracle Support provides customers with access to over a million knowledge articles and a vibrant support community of peers and Oracle experts.