External Early Start Date Does Not Populate In P6 (Doc ID 2801770.1)

Last updated on AUGUST 31, 2021

Applies to:

Primavera P6 Professional Project Management - Version 18.8 and later
Information in this document applies to any platform.

Symptoms


ACTUAL BEHAVIOR
---------------
External Early Start Date Is Not Populating in P6

EXPECTED BEHAVIOR
-----------------------
External Early Start Date Is Populating with value

STEPS
-----------------------
The issue can be reproduced at will with the following steps:
1. Import project Xer files in v18.
2. Check activity, there is value in External Early start date column.
3. If import into v19, check activity, there is no value in External Early start date column.

BUSINESS IMPACT
-----------------------
The issue has the following business impact:
Due to this issue, users cannot view External Early Start date.

Cause

To view full details, sign in with your My Oracle Support account.

Don't have a My Oracle Support account? Click to get started!


In this Document
Symptoms
Cause
Solution
References


My Oracle Support provides customers with access to over a million knowledge articles and a vibrant support community of peers and Oracle experts.