Duration Does Not Change When Changing Activity Start on Gantt Chart
(Doc ID 2804667.1)
Last updated on SEPTEMBER 03, 2021
Applies to:
Primavera P6 Enterprise Project Portfolio Management - Version 19.12.14.0 to 19.12.15.0 [Release 19.12]Primavera P6 Enterprise Project Portfolio Management Cloud Service - Version 19.12.14.0 to 19.12.15.0 [Release 19.12]
Information in this document applies to any platform.
Symptoms
ACTUAL BEHAVIOR
When dragging the start date of an unstarted activity on the Gantt Chart to make the start date earlier, the finish date is also being pulled, therefore keeping the Planned Duration constant.
EXPECTED BEHAVIOR
Expect the Planned Duration to increase and the finish date to remain constant.
STEPS
The issue can be reproduced at will with the following steps:
- Log into P6 Web.
- Open a project and drag the start date to an earlier date.
- Finish date will adjust earlier too and planned duration will not change.
Cause
To view full details, sign in with your My Oracle Support account. |
|
Don't have a My Oracle Support account? Click to get started! |