CMRO ASCP Plan Has Not Recommended Planned Orders For Non Standard Job Components (Doc ID 2808435.1)

Last updated on OCTOBER 01, 2021

Applies to:

Oracle Advanced Supply Chain Planning - Version 12.1.3.9.2 to 12.1.3.9.2 [Release 12.1]
Information in this document applies to any platform.

Symptoms

CMRO ASCP Plan

Business users observed that ASCP doesn't recommend planned orders for Non standard job material requirements.
Results are inconsistent - some Non standard jobs see planned order requirements.

This issue happening for constrained plan without detailed scheduling only for Non Standard jobs.

e.g.
ASCP / Supply Chain Plan / Workbench - query item and review pegging results

Non standard job are past due and planning engine moved the due date to Sysdate
Component requirements have no supply
Components have post processing LT  = 3 so that soonest supply will be on Day 3

Business requires setup for plan - MSO: Lead Time Control - DO_NOT_VIOLATE_MIN_PROC_TIMES

Business tried using MSO: Lead Time Control - VIOLATE_MIN_PROC_TIMES - but the plan would create new planned orders due on Day1 of plan even when we have firm supply on Day 3 and this is not acceptable.

 

Cause

To view full details, sign in with your My Oracle Support account.

Don't have a My Oracle Support account? Click to get started!


In this Document
Symptoms
Cause
Solution
References


My Oracle Support provides customers with access to over a million knowledge articles and a vibrant support community of peers and Oracle experts.