After Upgrade to 12.2.5 or higher - ATP Post Plan Processing Request Ends In Warning and the ATP Plan Run with 24x7 Setup is not Available in the Planner Workbench
(Doc ID 2810380.1)
Last updated on JULY 17, 2023
Applies to:
Oracle Global Order Promising - Version 12.2.5 and laterInformation in this document applies to any platform.
Symptoms
12.2.5 or later when upgrading from a lower release
This example was an instance upgraded from 12.1.3 to 12.2.9
ASCP (R) /Supply Chain Plan / Launch - pick ATP plan and launch with 24x7 enabled in parameters
All plan related requests complete with successfully, then the ATP Post Plan Processing request has Warning and does not launch the 24x7 ATP Switch Plan request - therefore the Plan is not available in form /Supply Chain Plan / Workbench
The following error was found in the ATP Post Plan Processing Request log file:
---------Before calling schedule---------
Exception in call to Call_Schedule
Return Status :
Error Message : ORA-06502: PL/SQL: numeric or value error: character to number conversion error
Unexpected Error. Sync Call To ATP failed
Sync Error: Unable to continue further
Changes
This is an instance which is upgraded from 12.1.3 to 12.2.9
Cause
To view full details, sign in with your My Oracle Support account. |
|
Don't have a My Oracle Support account? Click to get started! |
In this Document
Symptoms |
Changes |
Cause |
Solution |