NonStd Job Pegged To Lower Priority Demand (Doc ID 2819984.1)

Last updated on NOVEMBER 10, 2021

Applies to:

Oracle Advanced Supply Chain Planning - Version 12.2.9 and later
Information in this document applies to any platform.

Symptoms

On : 12.2.9 version, Planner workbench

ACTUAL BEHAVIOR
---------------
Non standard Job pegged to Lower Priority Demand

EXPECTED BEHAVIOR
-----------------------
Non standard job pegging should be as per the demand priority rule

STEPS
-----------------------
The issue can be reproduced at will with the following steps:
1. Log into Advanced Supply Chain Planner Responsibility
2. Navigate to Supply Chain Plan > Launch
3. Review the Plan Output of pegging for the problematic item


Cause

To view full details, sign in with your My Oracle Support account.

Don't have a My Oracle Support account? Click to get started!


In this Document
Symptoms
Cause
Solution
References


My Oracle Support provides customers with access to over a million knowledge articles and a vibrant support community of peers and Oracle experts.