Default Relationship Type to Finish Milestone Successor is SF not FF in P6 Professional (Doc ID 2825376.1)

Last updated on MAY 23, 2023

Applies to:

Primavera P6 Professional Project Management - Version 20.12.4.0 and later
Primavera P6 Enterprise Project Portfolio Management - Version 20.12.4.0 and later
Primavera P6 Enterprise Project Portfolio Management Cloud Service - Version 20.12.4.0 and later
Information in this document applies to any platform.

Symptoms

ACTUAL BEHAVIOR
---------------

The default relationship type when linking a Finish Milestone as a Successor is Start-to-Finish (SF).

Note: This occurs in 20.12.4 and 21.5 and later releases after a change to prevent invalid relationships from being added to milestones.

See: Beginning With Versions 20.12.4 & 21.5, P6 Will No Longer Allow The Creation Of Invalid Relationships To Start And Finish Milestone Activities (Doc ID 2785386.1)

 

EXPECTED BEHAVIOR
-----------------------

The default relationship type when linking a Finish Milestone as a Successor should be Finish-to-Finish (FF).

STEPS
-----------------------

  1. Open a project in P6 Professional
  2. Highlight two activities, the second of which is a Finish Milestone
  3. Right-click and link using Link Activities
  4. Resulting relationship type is SF

Cause

To view full details, sign in with your My Oracle Support account.

Don't have a My Oracle Support account? Click to get started!