Default Relationship Type to Finish Milestone Successor is SF not FF in P6 Professional
(Doc ID 2825376.1)
Last updated on MAY 23, 2023
Applies to:
Primavera P6 Professional Project Management - Version 20.12.4.0 and laterPrimavera P6 Enterprise Project Portfolio Management - Version 20.12.4.0 and later
Primavera P6 Enterprise Project Portfolio Management Cloud Service - Version 20.12.4.0 and later
Information in this document applies to any platform.
Symptoms
ACTUAL BEHAVIOR
---------------
The default relationship type when linking a Finish Milestone as a Successor is Start-to-Finish (SF).
Note: This occurs in 20.12.4 and 21.5 and later releases after a change to prevent invalid relationships from being added to milestones.
EXPECTED BEHAVIOR
-----------------------
The default relationship type when linking a Finish Milestone as a Successor should be Finish-to-Finish (FF).
STEPS
-----------------------
- Open a project in P6 Professional
- Highlight two activities, the second of which is a Finish Milestone
- Right-click and link using Link Activities
- Resulting relationship type is SF
Cause
To view full details, sign in with your My Oracle Support account. |
|
Don't have a My Oracle Support account? Click to get started! |
In this Document
Symptoms |
Cause |
Solution |
References |