EBS-PS: PS Solver Not Respecting Just In Time (JIT) Build Strategy Setup in Solve Stage Sequence When Scheduling Operations (Doc ID 2837244.1)

Last updated on JANUARY 27, 2022

Applies to:

Oracle Production Scheduling - Version 12.2.6 and later
Information in this document applies to any platform.

Symptoms

PS solver does not respect JIT build strategy setup in solve stage sequence rather uses pre-build DRA strategy to schedule the orders on the corresponding resources

Steps to reproduce:
1. Create a PS model and setup solve stages with 2 build strategies- Stage 1 uses Pre-build strategy for the first set of resources and Stage 2 uses Just In Time (JIT) strategy for the second set of resources.
2. Solve the model
3. Review the results and observe all orders scheduled on resources added to JIT solve stage sequence is pre-built and not schedule on time using JIT build strategy


Changes

 

Cause

To view full details, sign in with your My Oracle Support account.

Don't have a My Oracle Support account? Click to get started!


In this Document
Symptoms
Changes
Cause
Solution
References


My Oracle Support provides customers with access to over a million knowledge articles and a vibrant support community of peers and Oracle experts.