In P6 Web and Web Services, Adding a Project From an Existing Project Sometimes Results in Missing Team Member Activity Codes When Pasting into a Different EPS Node (Doc ID 2883113.1)

Last updated on AUGUST 18, 2022

Applies to:

Primavera Web Services - Version 18.8.23.0 to 18.8.25.5 [Release 18.8]
Primavera P6 Enterprise Project Portfolio Management - Version 18.8.23.0 to 18.8.25.5 [Release 18.8]
Primavera P6 Enterprise Project Portfolio Management Cloud Service - Version 22.1 to 22.7 [Release 22.1 to 22.7]
Primavera P6 Enterprise Project Portfolio Management - Version 19.12 to 19.12.19.1 [Release 19.12]
Primavera P6 Enterprise Project Portfolio Management - Version 20.12 to 20.12.15.0 [Release 20.12]
Information in this document applies to any platform.

Symptoms

ACTUAL BEHAVIOR

In P6 Web, when adding a project from an existing project, pasting the new project into a different EPS node sometimes results in specific activity codes and values not being copied over to the new project.

EXPECTED BEHAVIOR

All activity codes and values should be copied correctly to the newly added project.

 

The issue can be reproduced at will with the following steps:

  1. In P6 Web (Soap UI), configure Set Project Preferences > Team Member > Activity Updates.
  2. Select the desired Activity Codes to add that Team Member users can update, e.g. KPI.
  3. Note that the specific Activity Code KPI is missing in the new project.

Changes

 

Cause

To view full details, sign in with your My Oracle Support account.