Start Finish Time Moves 1 Minute Forward After Importing And Scheduling A Project
(Doc ID 2891078.1)
Last updated on AUGUST 26, 2022
Applies to:
Primavera P6 Enterprise Project Portfolio Management - Version 18.8 and laterInformation in this document applies to any platform.
Symptoms
ACTUAL BEHAVIOR
---------------
After importing a project and creating a baseline by copying the current project, the activity Dates (e.g. Start=08:01 vs. BL1 Start=08:00) show the 1min variance.
EXPECTED BEHAVIOR
-----------------------
The date/time remain exactly the same between the project and its baseline when the baseline is created by copying the current project.
STEPS
-----------------------
The issue can be reproduced at will with the following steps:
- Log into P6 Professional.
- Import a XER to create a new project.
- Create a baseline by copying the current project.
- Assign the baseline as Project and Primary Baseline.
- Open this project.
- Add Start, BL1 Start to the columns.
- It is observed that the Start and BL1 Start have 1min variance.
Cause
To view full details, sign in with your My Oracle Support account. |
|
Don't have a My Oracle Support account? Click to get started! |
In this Document
Symptoms |
Cause |
Solution |
References |