Cannot Add Relationship Between 2 Activities of 2 Different Projects
(Doc ID 2898860.1)
Last updated on OCTOBER 04, 2022
Applies to:
Primavera P6 Professional Project Management - Version 20.12.15.0 and laterInformation in this document applies to any platform.
Symptoms
ACTUAL BEHAVIOR
---------------
User cannot add relationship between activities of 2 different projects. On one project he has "Edit/create/delete activity relationship" permission, and he is the project super user of the other project.
EXPECTED BEHAVIOR
-----------------------
User should be able to add relationship between activities of 2 different projects.
STEPS
-----------------------
The issue can be reproduced at will with the following steps:
- Create 2 projects, say p1 and p2.
- Add activities to the projects.
- Grant "Edit/create/delete activity relationship" permission only to the user on p1.
- Grant "project superuser" profile to the user on p2.
- Open both projects.
- High-light an activity of p1, click "Assign" button in "Relationship" tab, try to select an activity of p2 and notice that the assign button is disabled.
Cause
To view full details, sign in with your My Oracle Support account. |
|
Don't have a My Oracle Support account? Click to get started! |
In this Document
Symptoms |
Cause |
Solution |
References |