Performance Degradation While Running a P6 Professional Report Based on Resource Assignment Data When Resource Analysis Preference "All Closed Projects" Is Enabled
(Doc ID 2901260.1)
Last updated on OCTOBER 13, 2022
Applies to:
Primavera P6 Professional Project Management - Version 20.12.14.0 and laterInformation in this document applies to any platform.
Symptoms
When executing a P6 Professional report based on Activity Resource Assignments, there is an extreme delay after the Loading Data / Loading Summary bar completes and before the report output is created/displayed, when the following User Preferences are set:
- Startup Filters > Resource Summary data is enabled
- Resource Analysis > All Closed projects (except what-if projects) is selected
The issue cannot be reproduced when the User Preferences > Resource Analysis > All Projects option is set to Opened projects only.
The issue can be reproduced at will using the following steps:
- Login to P6 Professional.
- Setup required user preferences:
- Click Edit > User Preferences.
- Click Startup Filters.
- Enable Resource summary data.
- Click Resource Assignments.
- Select All closed projects (except what-if projects).
- Click OK.
- Logout/Login to P6 Professional
- Import a project:
- Click File > Import....
- Choose XER format
- Import the file.
- Import the report:
- Click Tools > Reports > Reports.
- Right-click a report group and select Import....
- Import the file.
- Set Report Scope = Current ProjectReport.
- Run the report:
- Right-click Report > Run > Report.
- Choose Delimited Text File output then click OK.
- Note the reported performance issue.
Cause
To view full details, sign in with your My Oracle Support account. |
|
Don't have a My Oracle Support account? Click to get started! |