Duration of Regimens in Product And Duration in Event Tab Not Matching
(Doc ID 2930115.1)
Last updated on OCTOBER 02, 2023
Applies to:
Oracle Life Sciences Argus Safety - Version 8.2.3.2 and laterInformation in this document applies to any platform.
Goal
In Product information section below details are entered
Start Date time : 01-Oct-2000 00:00
Stop Date Time : 03-Oct-2000 00:00
Duration of Regimen gets populated as 2 days.
However when the same start and stop dates are entered in event section the duration gets calculated as 3 days.
What would cause this?
Solution
To view full details, sign in with your My Oracle Support account. |
|
Don't have a My Oracle Support account? Click to get started! |
In this Document
Goal |
Solution |
References |