Attachments Tab Has Dot Indicator Even Though Attachments Are Not Available
(Doc ID 2930907.1)
Last updated on FEBRUARY 24, 2023
Applies to:
Oracle Agile Product Collaboration - Version 9.3.6.0 and laterInformation in this document applies to any platform.
Symptoms
ACTUAL BEHAVIOR
---------------
Attachments tab has dot indicator even though attachments are not available on the all the PPM (Program, Phase, Task, Gate and Milestone) objects.
EXPECTED BEHAVIOR
-----------------------
Attachments tab should not have dot indicator if there are no attachments
STEPS
-----------------------
The issue can be reproduced at will with the following steps:
1. Create any PPM object.(Program, Phase, Gate, Task and Milestone)
2. Add attachments.
3. Click on “Save As” from Action Menu.
4. New object shows dot on Attachments tab but there are no attachments
Cause
To view full details, sign in with your My Oracle Support account. |
|
Don't have a My Oracle Support account? Click to get started! |
In this Document
Symptoms |
Cause |
Solution |