My Oracle Support Banner

EBS-PS: PS Solver Does Not Respect Firm Start Date Constraint Setup For the First Operation In the Routing (Doc ID 2937913.1)

Last updated on APRIL 17, 2023

Applies to:

Oracle Production Scheduling - Version 12.2.9 and later
Information in this document applies to any platform.

Symptoms

PS solver doesn't respect "Firm Start Date" constraint setup for the first operation in the routing but respects the "Firm Start Date" constraints for other operation in the routing.

Steps:
1. Setup a routing with multiple operations - 10, 20 through 100
2. Setup firm start date constraint for Operations 10, 40 and 80 and define the firm start date for each operation
3. Create a work order and solve the model
4. Observe PS doesn't respect firm start date constraint for operation 10 but respects firm start date for operations 40 and 80

Changes

Issue started with new PS 12.2.6 build C750

Cause

To view full details, sign in with your My Oracle Support account.

Don't have a My Oracle Support account? Click to get started!


In this Document
Symptoms
Changes
Cause
Solution
References


My Oracle Support provides customers with access to over a million knowledge articles and a vibrant support community of peers and Oracle experts.