P6 Professional Check Schedule Report - Baseline Execution Index (BEI) Is Not Correct
(Doc ID 2950231.1)
Last updated on MAY 19, 2023
Applies to:
Primavera P6 Professional Project Management - Version 22.12.1.0 and laterPrimavera P6 Enterprise Project Portfolio Management Cloud Service - Version 22.12 and later
Primavera P6 Enterprise Project Portfolio Management - Version 22.12.1.0 and later
Information in this document applies to any platform.
Symptoms
ACTUAL BEHAVIOR
---------------
The Baseline Execution Index (BEI) in the P6 Professional Check Schedule Report is generating an incorrect number of Baseline Activities, resulting in an incorrect BEI value.
EXPECTED BEHAVIOR
-----------------------
Baseline and BEI values should be correct.
STEPS
-----------------------
The issue can be reproduced at will with the following steps:
1. In P6 Professional, go to Tools / Check Schedule Report
2. Make sure BEI is checked / enabled.
3. Run report
Changes
Cause
To view full details, sign in with your My Oracle Support account. |
|
Don't have a My Oracle Support account? Click to get started! |