After Copying Activity Usage Spreadsheet Data and Pasting to a Microsoft XLS File, Some of the Copied Data Is Not Included.
(Doc ID 2964295.1)
Last updated on AUGUST 07, 2023
Applies to:
Primavera P6 Professional Project Management - Version 16.2.10.0 and laterInformation in this document applies to any platform.
Symptoms
ACTUAL BEHAVIOR
After copying Activity Usage Spreadsheet Data and pasting to a Microsoft XLS file, some of the copied data is not included.
EXPECTED BEHAVIOR
All time period data should be copied.
STEPS
The issue can be reproduced at will with the following steps:
- Login to P6 Professional.
- Open a project and navigate to Activity Usage Spreadsheet view.
- Open the Assign Baseline dialog and make sure a baseline is assigned as project baseline.
- In activity usage spreadsheet view, add "budgeted labor", "BL Project label" and "BL1 Labor" as the spreadsheet fields.
- Click any field, press CTRL A to select all data, press CTRL C to copy.
- Open an Microsoft XLS file --> create a new sheet --> press CTRL V to paste.
- Notice that some Time Period data is missing in the target Microsoft XLS sheet, while it exists in the P6 view and it has non-zero values for some activities.
Cause
To view full details, sign in with your My Oracle Support account. |
|
Don't have a My Oracle Support account? Click to get started! |
In this Document
Symptoms |
Cause |
Solution |
References |