When Copying and Pasting a Project, the Baselines Do Not Get Copied Over to the EPS Structure.
(Doc ID 2974879.1)
Last updated on SEPTEMBER 26, 2023
Applies to:
Primavera P6 Professional Project Management - Version 22.12 to 22.12.7.0 [Release 22.12]Information in this document applies to any platform.
Symptoms
ACTUAL BEHAVIOR
When copying and pasting a project, the baselines do not get copied over to the EPS Structure.
STEPS
The issue can be reproduced at will with the following steps:
1. Copy a project with the baseline check box selected.
2. Paste a project.
3. Observe the baselines do not get copied over to the EPS Structure.
Cause