When Copying and Pasting a Project, the Baselines Do Not Get Copied Over to the EPS Structure. (Doc ID 2974879.1)

Last updated on SEPTEMBER 26, 2023

Applies to:

Primavera P6 Professional Project Management - Version 22.12 to 22.12.7.0 [Release 22.12]
Information in this document applies to any platform.

Symptoms

ACTUAL BEHAVIOR

When copying and pasting a project, the baselines do not get copied over to the EPS Structure.

STEPS

The issue can be reproduced at will with the following steps:
1. Copy a project with the baseline check box selected.
2. Paste a project.
3. Observe the baselines do not get copied over to the EPS Structure.

Cause