Applies to:

Primavera P6 Enterprise Project Portfolio Management - Version 18.8.19.0 and later
Information in this document applies to any platform.

Symptoms

A child WBS level has the Project Security Profile privilege Edit Future Periods, but the parent WBS level does not.
A User who is assigned this Profile can manually update Future Period buckets in Project > Resource Assignments spreadsheet but when trying to change the curve from Manual to a different curve, they receive an error.
  

ERROR

You do not have the security privilege required to change an assignment's resource curve when the assignment has a manual resource curve.


STEPS TO REPRODUCE

The issue can be reproduced at will with the following steps:

  1. Login to P6 Pro.
  2. Open a Project.
  3. Go to Project > Resource Assignments.
  4. Add the "Curve" column.
  5. Select a Resource Assignment and notice there is no curve.
  6. Click on the Curve field and notice a curve can be added.
  7. Click on the spreadsheet bucket and notice that this can be edited.
  8. Manually update a Future Period bucket.
  9. Notice that the Curve changes from blank to "Manual".
  10. Click on the Curve field and receive error.

Changes

 

Cause

To view full details, sign in with your My Oracle Support account.

Don't have a My Oracle Support account? Click to get started!


In this Document
Symptoms
Changes
Cause
Solution
References


My Oracle Support provides customers with access to over a million knowledge articles and a vibrant support community of peers and Oracle experts.