Symptoms

ACTUAL BEHAVIOR
---------------
While running an MRP Plan, a recommendation is being made in the Planners Workbench to reschedule out a Purchase Order (PO) while another recommendation is made to create a new Planned Order when the current Purchase Order could be used instead.

The expectation is that the Purchase Order with the reschedule out recommendation should be used rather than creating a new Planned Order.

The issue can be reproduced at will with the following steps:

  1. Responsibility:  Material Planner
  2. Navigation:  MRP > Launch
  3. Enter the parameters to launch the plan



Cause

To view full details, sign in with your My Oracle Support account.

Don't have a My Oracle Support account? Click to get started!


In this Document
Symptoms
Cause
Solution
References


My Oracle Support provides customers with access to over a million knowledge articles and a vibrant support community of peers and Oracle experts.