Material Requirements Plan (MRP) Is Creating New Planned Orders While Rescheduling Out Existing Firm Supplies
(Doc ID 2993245.1)
Last updated on JANUARY 25, 2024
Applies to:
Oracle Materials Requirement Planning - Version 12.2 and laterInformation in this document applies to any platform.
Symptoms
ACTUAL BEHAVIOR
---------------
While running an MRP Plan, a recommendation is being made in the Planners Workbench to reschedule out a Purchase Order (PO) while another recommendation is made to create a new Planned Order when the current Purchase Order could be used instead.
The expectation is that the Purchase Order with the reschedule out recommendation should be used rather than creating a new Planned Order.
The issue can be reproduced at will with the following steps:
- Responsibility: Material Planner
- Navigation: MRP > Launch
- Enter the parameters to launch the plan
Cause
To view full details, sign in with your My Oracle Support account. |
|
Don't have a My Oracle Support account? Click to get started! |
In this Document
Symptoms |
Cause |
Solution |
References |