My Oracle Support Banner

MRP Is Allowing Release Of Planned Orders Of Items With The Release Time Fence Set To "Do not release (Auto or Manual)" (Doc ID 3018842.1)

Last updated on APRIL 25, 2024

Applies to:

Oracle Materials Requirement Planning - Version 12.2 and later
Information in this document applies to any platform.

Symptoms

Materials Requirement Planning (MRP) is allowing release of planned order of items for which the release time fence is set to "Do not release (Auto or Manual)".

Nav: Material Planner Responsibility -> MRP -> Workbench -> Select the plan -> Click on Supply\Demand -> Query the supplies of item to be released -> Check the Release check box for the planned order row -> Click on release.

See that the planned order is released successfully.

MRP should not to allow release of planned order (either manually or through auto-release) for such items.

Cause

To view full details, sign in with your My Oracle Support account.

Don't have a My Oracle Support account? Click to get started!


In this Document
Symptoms
Cause
Solution
References


My Oracle Support provides customers with access to over a million knowledge articles and a vibrant support community of peers and Oracle experts.