Activity Durations in Days Are Different When Project Baseline and BL1 Are the Same Project (Doc ID 3037291.1)

Last updated on SEPTEMBER 13, 2024

Applies to:

Primavera P6 Enterprise Project Portfolio Management - Version 23.12 to 23.12.6.0 [Release 23.12]
Primavera P6 Enterprise Project Portfolio Management Cloud Service - Version 24.1 to 24.7 [Release 24.1 to 24.7]
Information in this document applies to any platform.

Symptoms

ACTUAL BEHAVIOR
---------------
User Primary Baseline and Project Baseline are the same project, but are showing durations differently in days.

EXPECTED BEHAVIOR
-----------------------
User Primary Baseline and Project Baseline are the same project, and would show durations the same in days.

STEPS
-----------------------
The issue can be reproduced at will with the following steps:

  1. Import Projects and Schedule them separately.
  2. Add the older Project as a Baseline of the newer Project.
  3. Assign the Baseline as Project Baseline and User Primary Baseline.
  4. In Application settings, set Earned Value Calculations to At Completion.
  5. Add BL1 Start, Finish and Duration, Project Baseline Start, Finish and Duration columns to the Activity Layout => BL1 Duration does not match BL Project Duration.

Changes

 

Cause

To view full details, sign in with your My Oracle Support account.

Don't have a My Oracle Support account? Click to get started!


In this Document
Symptoms
Changes
Cause
Solution
References