BL Project Duration Changes Once Baseline Is Assigned
(Doc ID 3040065.1)
Last updated on AUGUST 09, 2024
Applies to:
Primavera P6 Enterprise Project Portfolio Management - Version 22.12.6.0 and laterPrimavera P6 Enterprise Project Portfolio Management Cloud Service - Version 22.12.6.0 and later
Information in this document applies to any platform.
Symptoms
ACTUAL BEHAVIOR
---------------
BL Project Duration changes once baseline is assigned
EXPECTED BEHAVIOR
-----------------------
Have same BL Project Duration after assign baseline.
STEPS
-----------------------
The issue can be reproduced at will with the following steps:
- Login P6 Client
- Open project, check issue activity, it has duration of 60 days.
- Go to Maintain Baseline to covert another project as it's baseline.
- Assign baseline project, when BL is assigned 'BL Project Duration' will show 63 days.
- Restore the baseline project, check its duration, shows 60 days.
Cause
To view full details, sign in with your My Oracle Support account. |
|
Don't have a My Oracle Support account? Click to get started! |
In this Document
Symptoms |
Cause |
Solution |
References |