BL Project Duration Changes Once Baseline Is Assigned (Doc ID 3040065.1)

Last updated on AUGUST 09, 2024

Applies to:

Primavera P6 Enterprise Project Portfolio Management - Version 22.12.6.0 and later
Primavera P6 Enterprise Project Portfolio Management Cloud Service - Version 22.12.6.0 and later
Information in this document applies to any platform.

Symptoms

ACTUAL BEHAVIOR
---------------
BL Project Duration changes once baseline is assigned

EXPECTED BEHAVIOR
-----------------------
Have same BL Project Duration after assign baseline.

STEPS
-----------------------
The issue can be reproduced at will with the following steps:

  1. Login P6 Client
  2. Open project, check issue activity, it has duration of 60 days.
  3. Go to Maintain Baseline to covert another project as it's baseline.
  4. Assign baseline project, when BL is assigned 'BL Project Duration' will show 63 days.
  5. Restore the baseline project, check its duration, shows 60 days.

Cause

To view full details, sign in with your My Oracle Support account.

Don't have a My Oracle Support account? Click to get started!


In this Document
Symptoms
Cause
Solution
References