Data Discrepency Between REST API /WBSSpread and P6 Professional Resource Assignment
(Doc ID 3041675.1)
Last updated on AUGUST 19, 2024
Applies to:
Primavera P6 Enterprise Project Portfolio Management - Version 22.12 and laterInformation in this document applies to any platform.
Symptoms
ACTUAL BEHAVIOR
---------------
There is a mis-match when invoking /spread/wbsSpread API to retrieve summarized WBS ActualLaborUnits, PlannedLaborUnits, CumulativeActualLaborUnits, CumulativePlannedLaborUnits, they are not aligned with the value from P6 Professional.
EXPECTED BEHAVIOR
-----------------------
Customer expects the data returned by REST API should be aligned with P6 Professional
STEPS
-----------------------
The issue can be reproduced at will with the following steps:
- Configure environment setting in P6 EPPM
- Summarization - Specify the interval to summarize and store resource spreads.
- Summarized by Calendar checked
- WBS Level: Week
- Resource/Role Assignment: Week
- Starting Day of Week - First day of week for calendars
- Monday
- Summarization - Specify the interval to summarize and store resource spreads.
- Summarize the project in P6 Professional
- Summarize to WBS Level: 0
- Open Resource Assignment
- Filter out material
- Add Actual Units, Budgeted Units, Cum Actual Units and Cum Budgeted Units
- Run REST API /spread/wbsSpread
- Notice the data difference: For example, Week Apr 17, 190.91 in P6 Professional, "ActualLaborUnits": 192.96, and "ActualNonlaborUnits": 11.666667 in REST API call
Cause
To view full details, sign in with your My Oracle Support account. |
|
Don't have a My Oracle Support account? Click to get started! |
In this Document
Symptoms |
Cause |
Solution |
References |