Data Discrepency Between REST API /WBSSpread and P6 Professional Resource Assignment (Doc ID 3041675.1)

Last updated on AUGUST 19, 2024

Applies to:

Primavera P6 Enterprise Project Portfolio Management - Version 22.12 and later
Information in this document applies to any platform.

Symptoms

ACTUAL BEHAVIOR
---------------
There is a mis-match when invoking /spread/wbsSpread API to retrieve summarized WBS ActualLaborUnits, PlannedLaborUnits, CumulativeActualLaborUnits, CumulativePlannedLaborUnits, they are not aligned with the value from P6 Professional.

EXPECTED BEHAVIOR
-----------------------
Customer expects the data returned by REST API should be aligned with P6 Professional

STEPS
-----------------------
The issue can be reproduced at will with the following steps:

  1. Configure environment setting in P6 EPPM
    • Summarization - Specify the interval to summarize and store resource spreads.
      1. Summarized by Calendar checked
      2. WBS Level: Week
      3. Resource/Role Assignment: Week
    • Starting Day of Week - First day of week for calendars
      1.   Monday
  2. Summarize the project in P6 Professional
    • Summarize to WBS Level: 0
  3. Open Resource Assignment
    • Filter out material
    • Add Actual Units, Budgeted Units, Cum Actual Units and Cum Budgeted Units
  4. Run REST API /spread/wbsSpread
  5. Notice the data difference: For example, Week Apr 17, 190.91 in P6 Professional, "ActualLaborUnits": 192.96, and "ActualNonlaborUnits": 11.666667 in REST API call

 

Cause

To view full details, sign in with your My Oracle Support account.

Don't have a My Oracle Support account? Click to get started!


In this Document
Symptoms
Cause
Solution
References


My Oracle Support provides customers with access to over a million knowledge articles and a vibrant support community of peers and Oracle experts.